				  Multiple Job Triggers | 
				     | 
			 
			
				Hi,
 
 
Is it possible to set up a job with both time and dependency triggers? Ie. job w to start not before 6:00, but also not before jobs x and y have completed?
 
 
I guess a workaround would be to set up an additional trigger job z to run at 6:00 and set that as an additional dependency for w, but that seems inefficient...
 
 
Thanks,
 
  Richard
  | 
			 
		  | 
	 
	
		| Fri Apr 12, 2013 9:11 am | 
		          | 
	 
	
		  | 
	 
	
		
			SysOp 
			Site Admin 
			
  
			
			
				Joined: 26 Nov 2006 Posts: 7992
  | 
			 
			  
		 | 
		
			
				   | 
				     | 
			 
			
				Sure. What you have described is one of the most common solutions because it allows managing dependencies graphically without coding. The little trick is to give job z a self describing name, something like "6 o'clock event"
  | 
			 
		  | 
	 
	
		| Fri Apr 12, 2013 9:51 am | 
		          | 
	 
	
		  | 
	 
	
		 | 
	 
 
  
	 
	    
	   | 
	