 |
SoftTree Technologies
Technical Support Forums
|
|
Author |
Message |
RichardDavis
Joined: 13 Nov 2012 Posts: 17 Country: United Kingdom |
|
Multiple Job Triggers |
|
Hi,
Is it possible to set up a job with both time and dependency triggers? Ie. job w to start not before 6:00, but also not before jobs x and y have completed?
I guess a workaround would be to set up an additional trigger job z to run at 6:00 and set that as an additional dependency for w, but that seems inefficient...
Thanks,
Richard
|
|
Fri Apr 12, 2013 9:11 am |
|
 |
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7948
|
|
|
|
Sure. What you have described is one of the most common solutions because it allows managing dependencies graphically without coding. The little trick is to give job z a self describing name, something like "6 o'clock event"
|
|
Fri Apr 12, 2013 9:51 am |
|
 |
|
|
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum
|
|
|