Saving causes the Job to run

 
Reply to topic    SoftTree Technologies Forum Index » 24x7 Scheduler, Event Server, Automation Suite View previous topic
View next topic
Saving causes the Job to run
Author Message
Robert Conatser



Joined: 02 Feb 2000
Posts: 28

Post Saving causes the Job to run Reply with quote

When I save a job the job will save and then start running. Is this normal and if so, can you turn it off?

Fri Sep 28, 2001 5:16 pm View user's profile Send private message
SysOp
Site Admin


Joined: 26 Nov 2006
Posts: 7948

Post Re: Saving causes the Job to run Reply with quote

This is a known bug that was fixed in recent versions. Please upgrade.

: When I save a job the job will save and then start running. Is this normal
: and if so, can you turn it off?

Fri Sep 28, 2001 6:34 pm View user's profile Send private message
Robert Conatser



Joined: 02 Feb 2000
Posts: 28

Post Re: Saving causes the Job to run Reply with quote

I'm running Version 3.1.0, is this the latest version?

: This is a known bug that was fixed in recent versions. Please upgrade.

Mon Oct 01, 2001 11:14 am View user's profile Send private message
SysOp
Site Admin


Joined: 26 Nov 2006
Posts: 7948

Post Re: Saving causes the Job to run Reply with quote

Yes, this is the last one. The bug I mentioned before caused some jobs with daily schedule types and "skip late" option disabled to run after the save. Is this your case or you are dealing with something else?

: I'm running Version 3.1.0, is this the latest version?

Mon Oct 01, 2001 11:28 am View user's profile Send private message
Robert Conatser



Joined: 02 Feb 2000
Posts: 28

Post Re: Saving causes the Job to run Reply with quote

Yes, this is probably the same problem. I've the job set to run daily with the skip late open not "on". I set this option "on" with a 10 minute delay and the log has a "skipped due to 4588 minute(s) delay. But if I change the delay to 99999 minutes the job will run when I save it.

: Yes, this is the last one. The bug I mentioned before caused some jobs with
: daily schedule types and "skip late" option disabled to run
: after the save. Is this your case or you are dealing with something else?

Mon Oct 01, 2001 11:35 am View user's profile Send private message
SysOp
Site Admin


Joined: 26 Nov 2006
Posts: 7948

Post Re: Saving causes the Job to run Reply with quote

Do not use values over 32767 as this is the maximum supported value for the maximum delay property, just enable the skip late job options.

Some notes:
Specifying 32767 for max delay is not reasonable anyway as it is more than 22 days - a value is too large for daily jobs anyway.

In 99999 case the value is converted to a negative number that would lead to unpredictable reasults.

On save all job start times and schedules are re-initialized and so jobs with such big intervals fall into late jobs category

: Yes, this is probably the same problem. I've the job set to run daily with
: the skip late open not "on". I set this option "on"
: with a 10 minute delay and the log has a "skipped due to 4588
: minute(s) delay. But if I change the delay to 99999 minutes the job will
: run when I save it.

Mon Oct 01, 2001 12:46 pm View user's profile Send private message
Robert Conatser



Joined: 02 Feb 2000
Posts: 28

Post Re: Saving causes the Job to run Reply with quote

I do not use this option anyway, I was trying it to see if it would stop the job from running.

BTW it was set to 9999 not 99999, mistake in typing.

I set it to 3600 (1 hour) and the job ran after I saved it.

: Do not use values over 32767 as this is the maximum supported value for the
: maximum delay property, just enable the skip late job options.

: Some notes: Specifying 32767 for max delay is not reasonable anyway as it is
: more than 22 days - a value is too large for daily jobs anyway.

: In 99999 case the value is converted to a negative number that would lead to
: unpredictable reasults.

: On save all job start times and schedules are re-initialized and so jobs with
: such big intervals fall into late jobs category

Mon Oct 01, 2001 12:54 pm View user's profile Send private message
SysOp
Site Admin


Joined: 26 Nov 2006
Posts: 7948

Post Re: Saving causes the Job to run Reply with quote

This is in minutes not in seconds, so 3600 is 60 hours. Please change it 60 minutes

: I do not use this option anyway, I was trying it to see if it would stop the
: job from running.

: BTW it was set to 9999 not 99999, mistake in typing.

: I set it to 3600 (1 hour) and the job ran after I saved it.

Mon Oct 01, 2001 12:58 pm View user's profile Send private message
Display posts from previous:    
Reply to topic    SoftTree Technologies Forum Index » 24x7 Scheduler, Event Server, Automation Suite All times are GMT - 4 Hours
Page 1 of 1

 
Jump to: 
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


 

 

Powered by phpBB © 2001, 2005 phpBB Group
Design by Freestyle XL / Flowers Online.