Job Forecast Report

 
Reply to topic    SoftTree Technologies Forum Index » 24x7 Scheduler, Event Server, Automation Suite View previous topic
View next topic
Job Forecast Report
Author Message
John Natale



Joined: 13 Sep 2000
Posts: 107

Post Job Forecast Report Reply with quote

24x7 Automation Suite version 3.0.5
Windows 2000 SP 2

Hello,

I have created a job that is scheduled to run once a week on Saturday.

The job does not appear in the job forecast report. If I add another day to run that has not occurred yet like Tuesday to the schedule for the Job it shows up as running Saturday then if I take Tuesday away Saturday disappears again.
Also, when I add Tuesday, Saturday is there but Tuesday is not. If I add Monday then Tuesday and Saturday are there but Monday is not.

I was just wondering if anyone would have an idea of why it is doing that?

John

Mon Aug 27, 2001 10:13 am View user's profile Send private message
SysOp
Site Admin


Joined: 26 Nov 2006
Posts: 7948

Post Re: Job Forecast Report Reply with quote

Do you mean that the first day/run is always skipped on the report? Does the job actually run on that day or the run is also skipped?

Do you have "collect job statistics" option enabled? If yes, for how long?

By the way, what do you have for the very first start date in the job properties?

: 24x7 Automation Suite version 3.0.5
: Windows 2000 SP 2

: Hello,

: I have created a job that is scheduled to run once a week on Saturday.

: The job does not appear in the job forecast report. If I add another day to
: run that has not occurred yet like Tuesday to the schedule for the Job it
: shows up as running Saturday then if I take Tuesday away Saturday
: disappears again.
: Also, when I add Tuesday, Saturday is there but Tuesday is not. If I add
: Monday then Tuesday and Saturday are there but Monday is not.

: I was just wondering if anyone would have an idea of why it is doing that?

: John

Mon Aug 27, 2001 11:06 am View user's profile Send private message
John Natale



Joined: 13 Sep 2000
Posts: 107

Post Re: Job Forecast Report Reply with quote

Yes the first day/run of a schedule is apperently always skipped so if you are only running one day a week it never shows up on the report since the report is only for one week. The job will actually run on the day. If you select the JOB DETAIL view for the Jobs tab is lists the correct next run date and time.

I have job execution statistics enabled if that is what you mean. For how long, always, it is never turned off.

I have tried the actual start date plus earlier dates and the result is the same.

John

: Do you mean that the first day/run is always skipped on the report? Does the
: job actually run on that day or the run is also skipped?

: Do you have "collect job statistics" option enabled? If yes, for
: how long?

: By the way, what do you have for the very first start date in the job
: properties?

Mon Aug 27, 2001 4:24 pm View user's profile Send private message
Display posts from previous:    
Reply to topic    SoftTree Technologies Forum Index » 24x7 Scheduler, Event Server, Automation Suite All times are GMT - 4 Hours
Page 1 of 1

 
Jump to: 
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


 

 

Powered by phpBB © 2001, 2005 phpBB Group
Design by Freestyle XL / Flowers Online.