Hi there,
This is for the java edition.
If I am running the master in nogui mode, would I have to stop the master to then run the master in gui mode?
I guess this applies to the agents as well.
Thanks,
Sean
|
|
Wed Jun 20, 2007 11:37 am |
|
 |
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7963
|
|
|
|
Yes, you should not run both at the same time from the same directory.
|
|
Wed Jun 20, 2007 12:03 pm |
|
 |
seanc217
Joined: 23 May 2007 Posts: 272
|
|
|
|
What would be the appropriate way to run the master?
I assume that most of the time you would run it in nogui mode in the background, then when you want to make changes or add jobs you would stop the scheduler and restart it in gui mode.
Is this correct?
What happens to jobs if the scheduler is stopped and restarted and the job was supposed to kick off when the scheduler was stopped?
Thanks again for the help,
Sean
|
|
Wed Jun 20, 2007 12:06 pm |
|
 |
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7963
|
|
|
|
The job will continue running while you are in the GUI mode. The GUI is not a separate utility. It is the same scheduler just run in a graphical mode.
Another way to modify jobs on-line is to use either command line console (can be started using console.sh or console.bat) or using web-based graphical console. Both consoles implement client-server mechanism between the console and the scheduler.
|
|
Wed Jun 20, 2007 12:56 pm |
|
 |
seanc217
Joined: 23 May 2007 Posts: 272
|
|
|
|
Maybe I'm confused here.
When I run in graphical mode, and I go to exit, the program asks me if I want to shut down. If I say yes the scheduler will stop correct?
How can I exit the graphical mode without shutting down the scheduler?
|
|
Wed Jun 20, 2007 1:19 pm |
|
 |
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7963
|
|
|
|
Yes, you need to stop it first
|
|
Wed Jun 20, 2007 2:08 pm |
|
 |
seanc217
Joined: 23 May 2007 Posts: 272
|
|
|
|
OK that's fine.
My last question is if when I have the scheduler stopped, if a job was to have kicked off during the time period when I have it stopped, when I re-start will the job kick off?
If not that's fine, we will have a time for maintenance.
Thanks again for all the help!!
|
|
Wed Jun 20, 2007 3:22 pm |
|
 |
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7963
|
|
|
|
No, they will no start. Time-based jobs will be missed in that event.
|
|
Wed Jun 20, 2007 4:19 pm |
|
 |
|