: 1. Make sure "Show job status display" option is disabled in : Tools/Options menu where is the "Show job status display" option? I Can't find it : 2. Set the job to run detached But detached requires more resources? We have 110 jobs scheduled running on 4 agents.....are you sure that running this job detached is not a problem? other difference betwen detached and none? i must be sure that only ONE job of the same tipe is executing in the same time. If a job detached is running the others of the same queue will start before the first one finished? : and set the job timeout to 15 minutes so that : the scheduler can kill it if it takes longer then that. But the job, if executed, finished properly (I found the end of the job on the scheduler log) : 3. Don't forget the restart the scheduler after you make these changes. : Hope that helps.
|