Hi, this is still an issue in 4.4 322 Multi-Platform, XP Pro.
I've just created a test job:
- Monthly Schedule
- Days: 9, 10, 11, 12, 13, 14, 15
- Start date: 9/09/2011
- Time: 5:00pm -- it's now 1645 on the 14th
Date of next run is showing as the 15th, should be 14th.
Please let me know you're still checking this thread. If no reply I'll start a new one.
Cheers
|
|
Wed Sep 14, 2011 12:49 am |
|
|
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7854
|
|
|
|
There are still some glitches in the graphical Wizard tool. To fix the schedule, change it for a moment to some other type, for example, change it to Daily, click finish, open the job again and change it back to Monthly. That should do it.
|
|
Wed Sep 14, 2011 10:19 am |
|
|
barefootguru
Joined: 10 Aug 2007 Posts: 195
|
|
|
|
Thanks, but no joy. Changed to Daily/Weekly, clicked Finish, then changed back to Monthly.
Still showing next run as 9th Oct, though should be today at 5pm (currently 0930 on the 15th).
|
|
Wed Sep 14, 2011 5:28 pm |
|
|
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7854
|
|
|
|
On my end, it seems to work ok.
|
|
Wed Sep 14, 2011 10:25 pm |
|
|
barefootguru
Joined: 10 Aug 2007 Posts: 195
|
|
|
|
Can you post the exact job settings you used? I'll see if it works for me.
|
|
Wed Sep 14, 2011 10:30 pm |
|
|
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7854
|
|
|
|
I tried reproducing your setup, except that I entered job start time 15 minutes after my system time, that was around noon here.
|
|
- Monthly Schedule
- Days: 9, 10, 11, 12, 13, 14, 15
- Start date: 9/09/2011
- Time: 5:00pm -- it's now 1645 on the 14th |
I then changed the schedule type, clicked Finish, reopened it, changed back to Monthly and it worked. Hope this helps
|
|
Thu Sep 15, 2011 1:18 pm |
|
|
barefootguru
Joined: 10 Aug 2007 Posts: 195
|
|
|
|
No joy.
Created monthly job with start date 18/09/2011 and time 3:00pm. Days 18, 19, 20, 21
Next run is showing as 20th, even though it's currently 1400 so should be today, the 19th.
Changed type to Daily or Weekly, clicked Finish. Next run is showing as today.
Changed type back to Monthly. Next run reverts to 20th.
It's an annoyance but can work around it in JavaScript unless you have a better idea.
Cheers
|
|
Sun Sep 18, 2011 10:42 pm |
|
|
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7854
|
|
|
|
Hi. What happens when you set the start date to an earlier date, for example, set to 01/09/2011 and days set to 18, 19, 20, 21?
|
|
Mon Sep 19, 2011 9:02 am |
|
|
barefootguru
Joined: 10 Aug 2007 Posts: 195
|
|
|
|
It runs if the start date is set to today, but not the 1st of the month or an earlier date.
Cheers
|
|
Mon Sep 19, 2011 4:35 pm |
|
|
SysOp
Site Admin
Joined: 26 Nov 2006 Posts: 7854
|
|
|
|
Thank you. I will add it to the opened support ticket..
|
|
Tue Sep 20, 2011 1:19 am |
|
|
|
|